Remove Chiller Vents and Thumb Nuts
- Remove both chiller vent panels.
- Unscrew all 5 thumb nuts:
- 3 from the left chiller vent
- 2 from the right chiller vent
-
Note: Bottom-right nut may be an 8mm hex nut—use socket if necessary.
|
|
Remove Rear Cover
- Slowly pull and wiggle the rear cover out through the vent openings.
|
|
Remove Chiller Mounting Nuts
- Using a 10mm socket remove the 4 nuts securing the chiller to the base frame:
- 2 on each side of the chiller base.
|
|
Remove E-Box Cover
- Use a 2.5mm hex screwdriver to remove the 4 screws securing the e-box cover.
|
|
Disconnect Electrical Components
- Disconnect Hanna Auto-Doser and LED connectors (press tab and pull from plastic base).
- Hanna wires: blue, brown, green/yellow.
- Some setups may use a Y-splitter.
- Disconnect UI ribbon cable from back of UI (spread wing tabs to release).
- Thread the LED wire out through its passthrough hole.
-
Tip: To free space, disconnect other wires from the hole temporarily and push them aside.
-
Warning: Never pull wires directly. pull only from connectors to disconnect.
|
|
Cut Electrical Zip Ties
- Cut zip ties securing:
- LED wire
- Power cord (if tied to the frame)
|
|
Disconnect Plumbing Manifolds
- Remove the 4 manifolds connecting chiller to tub:
-
Main Drain – under e-box, connects to lower plumbing
-
TH-1 – right of water filter housing
-
Flow Meter – connects from rear of water filter to bottom of heat exchanger
-
Heat Exchanger to Jet – top of heat exchanger to lower plumbing union
|
|
Remove Chiller
-
Warning: Move slowly. Use 2 people if needed.
- Grab handles on both sides of the chiller base.
- Carefully lift and walk the unit forward.
- Angle the top of the chiller back to clear the e-box from the tub wall.
|
|
Remove Main Drain Manifold From Water Pump
- Disconnect the main drain manifold from the in-port of the water pump.
|
|
Connect Main Drain Manifold To Water Pump
- Screw on the main drain manifold to the in-port of the water pump.
⚠️ Important: Ensure the black o-ring is in place under the ab union. No o-ring will result in a leak.
|
|
Install Chiller
-
Warning: Take your time—use two people if necessary.
- Tilt the top of the chiller back and slide the base into the cabinet.
- Lift and shift the unit until bolt holes align with frame.
- Slide bolts through chiller base.
|
|
Connect Plumbing to Tub
- Reconnect the 4 manifolds from the new chiller to the tub:
-
Main Drain → under e-box to tub plumbing
-
TH-1 → right side of filter housing
-
Flow Meter → rear of filter housing
-
Heat Exchanger to Jet → bottom plumbing union
-
Note: Confirm o-rings are present on the 2 unions connecting to lower plumbing.
|
|
Connect UI Ribbon to E-Box
- Plug ribbon into back of e-box—red stripe faces away from you (toward tub).
- Close the wing tabs to secure the cable.
- Route LED wire under left copper tube, across fan, and through original passthrough hole.
- Zip tie LED wire to bundle in front of fan.
- Route:
-
TH-1 and Flow Meter wires through back of e-box.
-
Hanna Auto-Doser wires behind chiller and into back of e-box cutout.
|
|
Connect Electrical Components
- Reconnect all components to their correct ports.
-
Double check all plugs before continuing.
-
Note: Do not install e-box or rear cover yet—testing comes next.
|
|
Test for Leaks & Error Codes
⚠️ Warning: The chiller fan is exposed during testing. Keep hands, tools, and loose items away from the fan to avoid injury or equipment damage.
- Fill the Plunge up with water so the water line is 6" below the edge of the tub.
-
🚨 Open the auto-doser ball valves🚨
- ⚠️ If chiller is turned on while auto-doser ball valves are closed it can damage the chiller.⚠️
- Plug in the Plunge and press the “Reset” button on the GFCI plug to power it on.
- Set temperature to 50 degrees so pump powers to 100%.
- Allow the Plunge to run and observe the chiller plumbing union connections.
- Carefully inspect all union fittings for any signs of leaking while the system is running.
- If a leak is found, pause the system and recheck that the union is properly seated and hand-tightened.
- Confirm no error code on UI
|
|
Power Down The Plunge
- Pause the chiller by pressing the pause button on the UI
- ⚠️ Powering down the Plunge while it's in a cooling cycle can damage the chiller.
- Press the test button on the GFCI outlet to power down the Plunge.
- Unplug the GFCI outlet from the outlet.
🚨 Important: Do not power down the Plunge before pausing the chiller.
|
|
Prepare for Rear Cover Installation
- Reattach e-box cover (4 screws).
- Secure chiller to frame using the 4 base nuts.
- Pre-install the upper thumb nut (near filter housing) loosely—this area is tight with cover on.
|
|
Install Rear Cover
- Carefully slide rear cover over chiller.
- Ensure power cord is routed through the correct side.
- Reinstall all 5 thumb nuts to secure rear panel.
- Attach the left and right chiller vents.
|
|
Comments
0 comments
Please sign in to leave a comment.